7.11.5. Explain Inventory Calculation Dialog
Explain inventory calculation dialog is designed to show and explain Streamline’s planning process for each planning item. This dialog discovers the simulation modeling behind a purchase, transfer, material requirements, and production plans generated by Streamline. It is especially useful to help understand the planning logic in the following complex cases as:
Description of the dialog
To open the Explain inventory calculation dialog:
Go to the Inventory planning tab.
Set the cursor at the planning item in question.
Press Ctrl + E, or right-click with the mouse and select the Explain calculation command from the context menu.
The Explain inventory calculation dialog appears (see figure below).
This dialog is divided into two parts. The top part shows the properties of the currently selected planning item. The bottom part, a table displaying events that will happen to the item in the future based on the input data (actual events) and Streamline's simulation modeling (simulated events).
The dialog has its own color-coding helping you understand the math behind the projected inventory levels.
Planning Item Properties
Debt received from lower echelon (current/max) shows the
current,
maximal, and
accumulated safety stock debts. The
current safety stock debt is calculated at the lower echelon and passed to the current echelon. The
maximal and the
accumulated safety stock debts are calculated at the current echelon.
Debt passed to upper echelon (current/max) displays the
current and
maximal safety stock debts that are calculated at the current echelon. The
current safety stock is passed to the upper echelon in the
two-echelon model. The
current and
max amounts
are calculated for each location in the two-echelon model.
Simulation horizon shows the number of periods to simulate ahead. This number is specific for each planning item and is not less than the
forecast horizon. To get all the necessary events calculated and shown within the
Purchase plan and
Projected inventory levels, Streamline extends the
Forecast horizon to a certain number of periods. This number is specific for each planning item and depends on the lead time and order cycle set for the planning item.
Table
Each column header of the table displays the date the particular
event happens. The date shown in the header of the first column indicates the date of the last imported
transaction. This date is also shown in the title of the Streamline application window.
Icon | Event |
| Placement of a transfer, purchase, or manufacturing order recommended by Streamline (simulation). |
| Arrival of the order planned by Streamline (simulation). |
| Arrival of actual purchase or transfer order. You can view this order in the To receive tab of the In transition details dialog. |
| Shipment of a sales order. You can view this order in the To ship tab of the In transition details dialog. |
| Item write-off (simulation). |
| End of the data aggregation period. |
Manufacture forecast shows the total consumption of the item (Material or Intermediate) got from the lower echelon. For example, assume we have a Material item which is used in two Finished items directly. In Streamline, relations between these items are represented by a two-echelon model, where the material is at the highest echelon and the finished products are at the lowest one. Consequently, the total demand for these two finished products is the manufacture forecast for the material.
Streamline doesn't take into account the consumption for the past period including the current date.
Safety stock shows how the calculated safety stock is spread out along the first order cycle period. If safety stock is
determined as the demand of the future periods, Streamline also shows safety stock for all the other order cycles by indicating the difference between the current and the previous order cycle.
Orders in transition row shows quantities that will be shipped to customers (negative values) and received to locations (positive values) within the simulation horizon. This row pulls information from the
To receive and
To ship tabs of the
In transition details dialog. These are
actual (not simulated) events that are going to happen.
Debt after arrival indicates the
accumulated safety stock debt for each subperiod.
Inventory + in transition. The main purpose of this row is to calculate and display the remaining on-hand level at the end of each order cycle period. Besides these goal quantities, the row displays how the on-hand level is decreased within each order cycle. These amounts are shown at the end of each subperiod. Streamline uses a
color-coding to explain how this row is calculated (see figure below). This row shows the current item
On hand in the first column of the table.
Projected inventory shows the projected inventory levels at the end of each subperiod. It is the sum of the
Inventory + in transition and
Planned order arrivals (see figure below). The values of this row shown at the end of each data aggregation period make up the
Projected inventory level report.
The first column of the table can be a little bit misleading, showing you an order placement (the email icon) on the past date. This is due to the
zero time point which is used as a starting point to run the simulation from. Do not pay attention to the date in the header of this column. Streamline always calculates the
Planned orders quantity for the first column on the
current date.
Effective inventory row is displayed in the ‘Explain calculation’ when replenishment strategy in Settings is set to Min/Max.
Effective inventory includes into calculation To receive and To ship, which are expected during the lead time. Streamline takes it into account instead of On hand when deciding when an order should be placed.
Buttons with Up and Down arrows on the right of the dialog allow navigating through the planning items.
Manufacture details option expands the table with all the items of the lower echelon which are linked to the current planning item based on the BOMs and shows the manufacture forecast for them.
Color-coding